Scope of work in which employees of Alpeng d.o.o. have participated: design for obtaining construction permit and detail design, design supervision of construction.

Specifications:
capacity | 9.350 PE |
---|---|
dry weather flow | 130 m³/h |
wet weather flow | 216 m³/h |
cleaning concept | SBR |
treatment level | N, DN, P |
sludge loading | 0,05 kgBPK5/kgSSd |
start of operation | 2014 |
investment cost | 3,0 mio EURO |